Bartlett’s $41 Million Sewer Project Could Unlock 300 Acres for Development

Sewer Improvements Address Development Constraints
Bartlett is preparing a $41 million sewer improvement project designed to support existing needs and accommodate future development in the Fletcher Creek Sewer Basin, an area north of U.S. 64 that has attracted interest from developers.
The work will include a third sewer equalization tank near the city’s fleet maintenance shop on Yale Road and a new gravity sewer system serving the basin.
The project traces back to a 2019 request from the City of Memphis for Bartlett to install three large equalization tanks to better manage wastewater discharge into Memphis’ sewer system. Two tanks, providing a combined 600,000 gallons of storage, were installed at the Union Depot mixed-use development in August 2022.
After studying the basin’s needs, Bartlett determined the third tank could be substantially smaller than originally requested.
“By the summer of 2024, all of our data results showed the third tank only needed to have a capacity of 1.5 million gallons, not the 5.6 million gallons requested by the City of Memphis,” said Bartlett Director of Engineering John Horne.
The new tank and associated piping are expected to provide approximately 3 million gallons of storage. Horne said the remaining site could also accommodate an expansion if additional capacity is needed in the future.
Infrastructure Investment Could Support Future Growth
The improvements are intended to provide the sewer capacity needed for development in the Fletcher Creek area. Approximately 300 acres within Bartlett Corporate Park have remained constrained by sewer infrastructure limitations since the mid-2010s.
Mayor David Parsons estimated the project could unlock $2.88 billion in economic activity.
The city recently approved the purchase of the specialized pipe for the storage tank directly from the manufacturer, a move expected to save more than $1 million compared with purchasing it through a contractor.
Project Timeline and Funding
Construction on the equalization tank is expected to begin in spring 2027, with completion anticipated by summer 2028. Work on the sewer gravity system is scheduled to begin in 2028 and continue through 2029.
Funding is expected to come from the city’s sewer fund, state and federal grants, and a proposed $21 million loan. The loan still requires approval from the Board of Mayor and Aldermen and would be repaid over 20 years.
Because the work will extend over several years, the city will continue pursuing grant opportunities to help fund the improvements.
Why It Matters
Sewer capacity is a fundamental requirement for development. By addressing infrastructure limitations in the Fletcher Creek area, Bartlett is positioning a significant amount of land for potential future investment, business expansion and job creation. The project is a long-term infrastructure commitment, not a guarantee that development will occur immediately.
Fast facts
- Estimated investment: $41 million
- Development area: Approximately 300 acres in Bartlett Corporate Park
- Tank construction: Expected to begin spring 2027
- Tank completion: Expected summer 2028
- Gravity sewer work: 2028–2029
- Proposed loan: $21 million, pending approval